STATUS REPORT
For Board Meeting August 19, 2010
1. Reclaimed Water Aquifer Storage Recovery
ASRus assisted EWD staff with preparation of the June 2010 monthly report to DEP’s Underground Injection Control Staff. Recovery from the ASR well began on May 5, 2010, and approximately 38 MG was recovered from the well. The well is currently shut-in, with a total of 756 MG in storage as of July 19, 2010. The allowable storage volume in the well is 820 MG. EWD has revised the residential reuse irrigation schedule to Tuesday, Wednesday, and Thursday.
*2. ASR Supplemental Reclaimed Water Source
FDEP issued a request for additional information on the permit modification submitted on May 23, 2010. ASRus worked with EWD staff to submit a timely response to FDEP addressing the issues raised. We are awaiting approval of the permit modification by FDEP. ASRus continues to work with EWD staff to equip the six new piezometers with water level recorders for continuous monitoring at the site to allow pumping of the storage pond once the permit modification is received and hydrologic conditions are favorable.
*3. DIW #1 & #2 2009 Annual Operating Report
The DIW annual operating reports were finalized after EWD’s comments were incorporated, and submitted to FDEP on April 23, 2010. At this time, PBS&J have not received any comments or request for additional information from DEP. PBS&J received the revised MOR reporting form modifications from FDEP and forwarded to EWD staff.
*4. 2010 R/O WTP DIW#1 MIT
The Mechanical Integrity Test (MIT) of the R/O WTP DIW #1 was completed on April 6, 2010. A Draft MIT report was submitted to EWD for review and comment. EWD’s review comments were incorporated into the report, which was finalized and submitted to FDEP on May 13, 2010. Currently awaiting any comments from FDEP. No comments received to date.
*5. 2009 Annual Wellfield Management Report
The 2009 Annual Wellfield Management Report was submitted March 30, 2010. On June 25, 2010, EWD received 13 comments on the report from SWFWMD. PBS&J will review the comments and respond to SWFWMD by September 25, 2010.
6. GIS/GPS
GPS information has been completed on the fire hydrants and water main valves as of March 23, 2010. A data base has been created for Charlotte County area to connect the water mains to the fire hydrants and valves. The entire distribution system in Charlotte County is completed. Work for the project is on hold in order to work on the program upgrade for an internal web site of the mapping to be used by EWD personnel only. A presentation was given at the Manager’s Meeting held August 11, 2010.
*7. Force Main Modeling
EWD staff has begun work on the modeling of the 6 inch force main, this portion of the backbone of the pipes has been completed. EWD staff is now reviewing the record drawings and gathering pertinent information to combine with the 6 inch backbone portion. Work for the modeling is on hold in order to work on the program upgrade for an internal web site of the mapping to be used by EWD personnel only.
8. Water Main Extension
This will be a EWD in-house project. The areas involved are Loralin Drive, Punta Nova Terrace and Cardinal Lane in Charlotte County and Olive Avenue, Cedar Avenue and Bay Park Drive in Sarasota County. The work has been completed on the watermains for Loralin Drive and Punta Nova Terrace. The mains have been disinfected, hydrostatically and bacteriologically tested with satisfactory results and have DEP clearance. Work has been completed at Cardinal Lane. The DEP clearance was submitted August 10, 2010. The main has been installed on Cedar Avenue and bacteriological testing will be completed the week of August 16, 2010.
9. South Manasota Key Drainage Improvement (Phase 1) and (Phase 2)
The project started February 8, 2010. Construction was completed on July 28, 2010. Because the new water main was extended significantly beyond the length specified in the DEP permit, a permit modification will be required in order to receive final clearance for the project. As built drawings of the completed work have been received and are being transferred to the plan set for submittal to FDOH by August 20, 2010. The submittal will require a $500 application fee. Installation of drainage culverts is continuing.
10. Dearborn Street Drainage Project
EWD will be working with DMK on a redesign of the Dearborn Street Drainage Project. DMK will be removing various sidewalks in the vicinity of Dearborn from the Englewood project and designing them in the Dearborn project. At the July 15, 2010 Board Meeting, the Board approved additional money for FY 10 Budget, as well as the DMK Task Order for the design to relocate EWD facilities within the County project. This project will have Joint Project Agreement with Sarasota County. DMK started on the design of relocating EWD facilities on July 29, 2010 and anticipate having review plans in two weeks and submitting for DEP permits in three weeks.
11. Winchester South Project
EWD staff was contacted by Joanne Vernon, P.E. CC Stormwater Manager letting us know that Charlotte County is planning to go to construction next summer with this project. EWD staff will work with the County on the Joint Project Agreement for this project. GWE is the Engineer for the District. This project is part of the FY10 CIP Budget.
*12. Philman Mining Permit AKA Winchester Lakes
EWD reviewed the Construction Plans prepared by DMK on February 3, 2010. Clarifications and/or corrections were requested by EWD staff and completed by DMK. The permits were executed on February 12, 2010 and sent to DMK for submittal to DEP. The DEP Wastewater Permit was received March 3, 2010. The Developer Agreement was sent March 9, 2010.
*13. Charlotte County Sidewalks
EWD staff reviewed the Manor Road Sidewalk 60% Construction Plans. There were water and sewer conflicts found. A letter listing the conflicts was sent to Johnson Engineering on June 2, 2010.
*14. SR 776 from San Casa to Sunnybrook Blvd. Landscape Project
DOT has a landscape project on SR 776 from San Casa to Sunnybrook. EWD staff reviewed the plans and there will be no interference with EWD facilities in the area. A letter was sent to DOT on February 17, 2010 stating there will be no interference with our facilities; however, the District’s Locator will be on site when the landscaping begins to assist the contractor with any questions concerning our utilities.
*15. Sarasota County Water Interconnect
Sarasota County contacted EWD staff on April 21, 2010 stating that they have completed the review of the preliminary report on the interconnect and the Interlocal Agreement. The Interlocal Agreement was approved at the Sarasota Board of County Commissioners Board Meeting held on June 8, 2010.
*16. Sarasota County Regional Advanced Traffic Management System
EWD staff was contracted by the Engineering Firm on behalf of Sarasota County to inform the District that they will be installing conduit and fiber optic lines at the traffic intersections throughout the Englewood Water District along SR 776. A preliminary set of the construction plans was submitted. The County will be contacting the utilities in this project area for a pre-construction meeting. The anticipated construction start date for this work is November, 2010.
*17. Sarasota County Bus Stops
EWD staff was contracted by Stanley Consultants, Inc. on behalf of Sarasota County and Sarasota County Area Transit to inform the District that they will be installing bus stop in the area of the Englewood Hospital. They have included the relocation of one of the fire hydrant in this project. A preliminary set of the plans was submitted for EWD staff to review. The review was completed and a response sent to the consultant July 28, 2010.
18. Elevated Tank Painting Project (COMPLETION DATE: November 4, 2010)
The Contractor started moving the equipment in over the 4th of July weekend. The Contractor’s crew started prepping the site on July 6, 2010 and started working on the inside of the water tank on July 7, 2010. The tank has been painted, however, the lettering color is not the color requested. There will be a second crew on site the first or second week of August. This crew will put the correct color on the lettering and will clean up the project area. The project will be inspected prior to final clean up. The District signed off on the project on August 3, 2010 and the warranty period has begun. A pin hole was found after the water tank was filled. The Contractor was notified of the problem and must repair the hole as a warranty item.
19. Vacuum Sewer Telemetry Project
The system has been installed. Initial testing will proceed in August 2010.
20. Engineer Library
EWD has 8 engineering firms in its original library of 10. The original Agreement with these engineering firms consists of a base 3 year term with the option 2 consecutive one year extensions. The first one year extension ends this September 1, 2010. As stipulated in the Agreement, the second year extension letter was sent thirty (30) day prior to expiration. Acceptance was received from 7 of the 8 engineering firms. If the final engineering firm does not respond by September 1, 2010, the firm will be removed from the library. Before the expiration of the final year’s extension, the District will advertise a Request for Letters of Interest as required by CCNA to choose the new EWD Engineer Library.
*NO CHANGE IN STATUS